Sinohydro Jiangsu Power Construction No.1 Company Successfully Commissions 110kV No.2 Oil Refining Central Substation for Shenghong Refining-Petrochemical Integration Project
As the power hub for critical facilities (crude distillation, thermal systems, catalytic cracking, etc.), this substation overcame challenges including:
Challenge 1
4×110kV transformers
120MW total capacity
Challenge 2
Complex power
distribution networks
Our cable conveyors played a pivotal role
Our highlights
Technical Innovation
Coordinated multi-machine operation enabled 500m+ large-section cable installation in confined pipe racks, eliminating manual-dragging risks.
Our highlights
Efficiency Gains
300% daily progress acceleration, completing 110km cables 15 days ahead of schedule.
Our highlights
Smart Safety
Real-time monitoring of tension/side pressure achieved zero sheath damage, with one-time success at 30 complex bends.